This afternoon, the Manistique DDA met to discuss further ideas concerning improvements to
the municipal marina and adjacent property. A third conceptual painting of the entire project was
introduced. Several other smaller conceptual paintings were the focus of discussion: a widened and
more open area where the boardwalk passes below the US2 bridge, a previously considered stressed
fabric pavilion design and a conventional pavilion design. Manning the gavel, Bill Hentchell
emphasized that all reasonable ideas, consistent with the goal of improving the marina area, were
welcome for consideration. He stated the goal of the considered marina project is to improve the
value of the marina area to most residents and tourists; thus making Manistique more competitive
among lake shore communities.
07/17/01
At the Manistique D.D.A. meeting today, a representative of U.P. Engineers and Architects Inc.
presented early estimates of the costs associated with various facets of the considered
Manistique marina park improvements. He emphasized the fact that without more specifics
concerning quality, quantity, size, labor, etc., the estimates should be considered as very
rough "guesstimates" at current prices, but they would provide the D.D.A. with some comparative
numbers to consider. The guesstimate information follows:
MANISTIQUE WATERFRONT PARK
PRELIMINARY COST ESTIMATE
WALKWAY UNDER BRIDGE
Concrete Walk (9600 s.f.) 2.74 $26,304
Widen Existing Walkway (100 I.f.) Lump Sum 24,000
Lighting (10) $3,000 each 30,000
Landscaping, Trees, Site Furnishings,
Signage Lump Sum 10,000
SUBTOTAL $90,304
Contingency (10%) 9,000
Design, Bid Documents, Construction Administration
(15%) 13,545
TOTAL $112,849
MANISTIQUE WATERFRONT PARK
PRELIMINARY COST ESTIMATE
PARK DEVELOPMENT
Seawall Mooring Area (300 I.f.) 1000 l.f. $300,000
Stone Riprap (400 l.f.) Lump Sum 20,000
Concrete Walkways (14,400 s.f.) 2.74 39,456
Parking Improvements (100 cars) Lump Sum 44,000
Access Improvements Lump Sum 30,000
Lighting (40) $3,000 each 120,000
Sitework/Grading Lump Sum 30,000
Utilities Lump Sum 20,000
Pavilion, Wood (3200 s.f.) Lump Sum 120,000
Alternate Tensile Fabric Structure
Add $75,000
Restrooms/Service Building Lump Sum 120,000
Landscaping, Trees, Site Furnishings,
Signage Lump Sum 100,000
SUBTOTAL $943,456
Contingency (10%) 94,345
Design, Bid Documents, Construction Administration
(15%) 141,518